§ 122-219. Conformance with approved plan; changes to approved plan; certification of compliance; maintenance of improvements.  


Latest version.
  • (a)

    Conformance with approved plan. Upon the site plan being approved and a building permit being issued, the development shall be built substantially in accordance with the site plan and the plans and specifications.

    (b)

    Changes to approved plan. If the owner or his agent, or successors, desire to make any changes to an approved site plan, such proposed changes shall first be submitted to the building official.

    (1)

    If the building official deems that there is substantial change or deviation from that which is shown on the approved site plan that will affect concurrency, the owner or his agent must submit a new site plan for review by the site plan review committee.

    (2)

    If, after consultation with affected departments, the building official deems the changes to not be substantial, the changes will be allowed to be made without additional review. A record of the changes must be made part of the permanent record of the site. At the discretion of the building official, this can be accomplished by either submitting a revised site plan or making handwritten corrections to the original plan. Handwritten corrections must be signed and dated by the owner or his agent and a representative of the city.

    (c)

    Certification of compliance. After completion of the improvements in accordance with the approved site plan and specifications, but prior to the issuance of any certificate of occupancy or final approval relating to the site, a registered engineer or other professional authorized by Florida Statutes to make such certification shall verify that the actual construction is in compliance with and functions in the manner of the approved site plan.

    (1)

    If the construction is in substantial compliance with the approved site plan, a registered engineer or other professional authorized by Florida Statutes to make such certification shall submit a signed and sealed certification, as follows, to the building official:

    PROFESSIONAL'S
    CERTIFICATION:

    I, ___________, do hereby certify that I have made a final review of the construction of ___________ site development located at ___________ and the actual construction is in substantial compliance with and functions in the manner of the approved site plan.

    _____
    Signature
    _____
    Name (Please Type), Date

     

    (AFFIX SEAL)

    Florida Registration No. _______

    (2)

    If the construction is not in substantial compliance with the approved site plan, the construction shall either be corrected to make it conform with the approved site plan and then be certified by a registered engineer or other professional authorized by Florida Statutes to make such certification, or a new site plan may be resubmitted for review by the site plan review committee.

    (3)

    All as-builts submitted to the city subsequent to the date of aerial photography of that local area in which the project is located must be drawn to a scale of one inch equals 100 feet, with two-foot contours, and verified with spot elevations. These as-builts must conform to the standards set forth by section 21-HH-6, Florida Administrative Code, pursuant to F.S. § 472.027.

    (4)

    The city will accept an as-built certification from a registered surveyor who has the authority to submit the certification as defined by the Florida Statutes.

    (d)

    Maintenance of improvements. After completion of the improvements in accordance with the approved site plan and subsequent issuance of the certificate of occupancy, all improvements shall be perpetually maintained by the owner, successor or heirs, as shown on the site plan.

(Code 1985, § 7-1044; Ord. No. 2275, § 77, 5-5-92; Ord. No. 2731, § 1, 5-27-97)